Our team has been working with Grand Erie District School Board since 2003 and WT Infrastructure has continued to work with the Board with their rural water systems. At the request of the Board, our team prepared an asset management inventory and renewal plan to upgrade and replace the original designs completed by our staff 20 years ago. The project is a multi-year project that includes upgrades to filter and UV systems, replacement of parameter specific equipment and expansion of systems to address school population changes. With each system change, an updated Engineering Evaluation Report was prepared to comply with O.Reg. 170/03.
Location
Brant, Haldimand and Norfolk County, ON
Lead Engineer
Jamie Witherspoon
Capital Cost
$200K
Design
2021